FEB 24 2000

MEMORANDUM FOR ALL SERVICE CENTER DIRECTORS

FROM:

William R. Yates
Deputy Executive
Office of Field Operations
Immigration Service Division 

SUBJECT:  FY2000 Service Center Adjudications Priorities

In an effort to provide our customers with consistent service and expectations, the following adjudication priorities are being established for all service centers:

Form Processing Time
   
I-131 30 DAYS
I-129L 30 DAYS
I-129 (All other) 60 DAYS
I-765  Card order sent within 75 DAYS
C-8 ASYLEE Card order sent within 21 DAYS
I-90  Card order sent within 95 DAYS
I-130 (Immediate relative or visa number available) 90 DAYS
I-140 (Visa number available) 90DAYS
I-526 90 DAYS
I-485 Commissioner's Targeted Priority Goal
N-400 Commissioner's Targeted Priority Goal

 

All other applicants/petitions should be completed within 180 days.